Practice Free MB-335 Exam Online Questions
You need to enable the features and configuration keys for the firepits.
Which two features should you enable? Each answer presents part of the solution. NOTE: Each correct selection is worth one point
- A . Engineering attributes
- B . Change management for process manufacturing
- C . Engineering product variants
- D . Engineering change management
- E . Production floor execution management
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.
The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. IngredientA is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient
You need to ensure that the system is set up to support the manufacturing process.
Solution: Create a formula version for each concentration level.
Does the solution meet the goal?
- A . Yes
- B . No
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen
A client subcontracts production work to a vendor for production operations.
You need to model subcontracting of route operations in production orders.
Solution: Ensure that the material routing process is independent of the services procurement process.
Does the solution meet the goal?
- A . Yes
- B . No
A manufacturing company is implementing production in Dynamics 365 Supply Chain Management. The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view. You need to configure the system to meet the requirements.
Which three options should you configure? Each answer presents a partial solution. NOTE: Each correct selection is worth one point.
- A . Capable to Promise
- B . finite capacity
- C . bottleneck resource
- D . operations scheduling
- E . job scheduling
An electronics manufacturing company is transitioning from infinite capacity planning to finite capacity planning to improve scheduling efficiency and manage resource constraints effectively. The company observes that its manufacturing process typically requires a minimum lead time of five days.
The company requires finite capacity scheduling to create realistic production schedules that account for resource limitations over a defined minimum lead time of five days.
You need to implement finite capacity planning with a time fence that aligns with the five-day manufacturing lead time.
Solution: Disable capacity reservations when scheduling production orders.
Does the solution meet the goal?
- A . Yes
- B . No
DRAG DROP
A glass bottle manufacturer uses route operations to schedule resources and track manufacturing costs.
The company has recently seen an increase in demand and purchases another resource that costs more to run. The company uses the same costs per resource. The company must be able to track cost contributions for the new resource.
You need to create a cost category for the new resource.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order. NOTE: More than one order of answer choices is correct You will receive credit for any of the correct orders you select.


A company plans to use master planning in Dynamics 365 Supply Chain Management. The company will sell items between legal entities.
The company has several facilities across legal entities that can manufacture the same products. Same products are produced only in some plants. To meet product demand, when one facility is over capacity, another facility is used to fulfill the downstream demand.
The organizational entities are:
• LegalEntityA: Plant 1.2, and 3
• LegalEntityB: Plant4and 5
• LegalEntityC: Plant 6. 7, and 8
The following plants must be planned together:
• Plant 1. Plant 3. and Plant 4
• Plant 2. Plant 6. and Plant 8
• Plant 5 and Plant 7
You need to configure master planning for the facilities.
Which configuration mechanism should you use?
- A . Production groups
- B . Item model groups
- C . Coverage groups
- D . Intercompany planning groups
D
Explanation:
The configuration mechanism that you should use is Intercompany planning groups.
Here is the explanation:
Intercompany planning groups are groups of companies that are planned together in master planning. Intercompany planning groups allow you to include planned downstream demand from other companies in your master plan, and also to peg across companies by using multilevel pegging1. You can use intercompany planning groups to plan for intercompany sales and purchases, and to optimize the production capacity across companies1.
In this scenario, you need to configure master planning for the facilities that must be planned together. To do this, you should create intercompany planning groups that include the relevant plants from different legal entities. For example, you can create an intercompany planning group that includes Plant 1, Plant 3, and Plant 4 from LegalEntityA and LegalEntityB. You can also specify the scheduling sequence for the companies in the intercompany planning group, which determines the order in which master planning is run for each company1.
The other options are not correct, because they do not involve intercompany planning. Production groups are groups of production orders that share the same parameters, such as ledger accounts and posting profiles2. Item model groups are groups of items that share the same inventory policies, such as reservation, tracking, and costing3. Coverage groups are groups of items that share the same coverage settings, such as coverage code, period, and time fence.
1: Intercompany planning 2: Production groups 3: Item model groups: [Coverage groups]
A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.
The production planner increases the lead time of an item. On the next master planning output the planner receives a cancel action message on existing purchase orders. The message includes a suggested earlier date for the planned purchase orders.
The demand for the item has not changed since the original purchase order was placed. Dynamic negative days is not used.
You need to resolve the issue.
What should you do?
- A . Increase positive days.
- B . Decrease positive flays.
- C . Decrease negative days to be less than the item lead time.
- D . Increase negative days to be greater than the item lead time.
DRAG DROP
A company has manufacturing sites that process different types of production orders using highly specialized equipment.
Released production orders have been processing for an excessive amount of time while the system tries to find a viable route that conforms to the constraints specified in the system.
The system must automatically time out if a viable solution is not found after 120 seconds.
You need to configure the automatic timeout.
Which form should you use for each configuration? To answer, drag the appropriate forms to the correct configurations. Each form may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content. NOTE: Each correct selection is worth one point.


You are the production supervisor at a chemical processing plant.
You must track attributes for each batch of chemicals. Automated quality orders must be generated when a batch order for these chemicals is reported as finished.
You need to ensure that the values of attributes are updated and tracked.
What three actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
- A . Create a test instrument for each attribute.
- B . Create attribute types.
- C . Assign the attributes to the chemicals.
- D . Assign the attributes to the appropriate test on the test group.
- E . Set up batch attributes.