Practice Free PSPO-II Exam Online Questions
During the product’s development effort, the market for which the product is being built has changed and evolved.
What should you do? (choose the best answer)
- A . The Product Backlog should remain unchanged. Move the product to a more suitable market as you have already made investments in product development.
- B . Make changes to the Product Backlog to reflect what is needed to deliver the most value
- C . There is no impact as the commitment is to deliver on the approved project plan.
- D . Replace the current Product Backlog with a new Product Backlog that fits the updated market.
B
Explanation:
The Product Backlog is a living artifact and continuously evolves throughout the lifespan of the product.
One of the principles of agility is to harness change for the customer’s competitive advantage.
During the product’s development effort, the market for which the product is being built has changed and evolved.
What should you do? (choose the best answer)
- A . The Product Backlog should remain unchanged. Move the product to a more suitable market as you have already made investments in product development.
- B . Make changes to the Product Backlog to reflect what is needed to deliver the most value
- C . There is no impact as the commitment is to deliver on the approved project plan.
- D . Replace the current Product Backlog with a new Product Backlog that fits the updated market.
B
Explanation:
The Product Backlog is a living artifact and continuously evolves throughout the lifespan of the product.
One of the principles of agility is to harness change for the customer’s competitive advantage.
A new competitor has joined the market and has quickly gained market share, which leads to a loss of sales. After investigating, you have found out that the new competitor can release to the market faster than you three times.
What is the best first response? (choose one best answer)
- A . Add new features you think that can attract new customers to the next release.
- B . Launch the promotion campaign and reduce the product’s price to attract more customers.
- C . All of the above
- D . Improve your Time-to-Market to compete with the competitor
D
Explanation:
The current situation that the new competitor is faster than you in releasing the product. The only way to win the customers is to improve your Time-to-Market (the faster, the better). Frequent releases help the firm stay relevant to the market and can frequently gauge the customer’s satisfaction. Most software companies favor the Sprint of 2 weeks to deliver the outcome to customers faster.
Which of the following is true for the Current Value – Key Value Area in Evidence Based Management from Scrum.org? Choose the best answer
- A . It expresses the organization’s ability to quickly deliver new capabilities, services, or products
- B . It expresses the ability of a product development organization to deliver new capabilities that might better meet customer needs
- C . It reveals the value that the product delivers to customers, today
- D . It suggests the potential future value that could be realized if the organization could perfectly meet the needs of all potential customers
C
Explanation:
Current Value reveals the value that the product delivers to customers, today.
The CEO questions Mike, the Product Owner, on the data showing the usage rates. He believes feature usage is not the right measure. You are the Product Owner, you have confirmed that the data is accurate and determine that the data is valuable to the team and product.
What should you do? (choose the best answer)
- A . Continue to measure the usage feature but not publish the data.
- B . Continue to measure and publish the data and use it to inform your decisions.
- C . Stop measuring to appease the CEO.
B
Explanation:
Values of Scrum: openness and transparency. It means you have to publish your data, your result to stakeholders (transparency = everyone is on the same page, openness = let them discuss the results). Then use the data to inform your decisions.
True or False: Release Frequency means: The time spent correcting product problems between the point the developers say it is ready to release and the point where it is actually released to customers.
- A . FALSE
- B . TRUE
A
Explanation:
Release Frequency: The number of releases per time period, e.g. continuously, daily, weekly, monthly, quarterly, etc. This helps reflect the time needed to satisfy the customer with new and competitive products.
Release Stabilization Period: The time spent correcting product problems between the point the developers say it is ready to release and the point where it is actually released to customers.
True or False: Michael, a new Product Owner, has been assigned to work in the Finance industry, which is new to him. He is unsure about the market desires and customer needs. The Product Manager advised Michael to conduct experiments, validate customer needs, start doing smaller releases more often.
- A . True
- B . False
A
Explanation:
As uncertainty is high, conducting experiments is the best way to test your hypothesis. Smaller releases also minimize the risk and help the Product Owner adjusts the product’s strategy.
What questions might the Developers use at the Daily Scrum? (choose the best three answers)
- A . How many hours did I spend on the project yesterday?
- B . What impediments are in my way or in the way of the team?
- C . Why were you late?
- D . How many meetings did you have yesterday?
- E . What work am I going to do today to help the team achieve its goal?
- F . What work did I do yesterday to help the team achieve its goal?
B,E,F
Explanation:
The Developers can select whatever structure and techniques they want, as long as their Daily Scrum focuses on progress toward the Sprint Goal and produces an actionable plan for the next day of work. This creates focus and improves self-management.
The Developers can use for instance these questions if they want.
What questions might the Developers use at the Daily Scrum? (choose the best three answers)
- A . How many hours did I spend on the project yesterday?
- B . What impediments are in my way or in the way of the team?
- C . Why were you late?
- D . How many meetings did you have yesterday?
- E . What work am I going to do today to help the team achieve its goal?
- F . What work did I do yesterday to help the team achieve its goal?
B,E,F
Explanation:
The Developers can select whatever structure and techniques they want, as long as their Daily Scrum focuses on progress toward the Sprint Goal and produces an actionable plan for the next day of work. This creates focus and improves self-management.
The Developers can use for instance these questions if they want.
What questions might the Developers use at the Daily Scrum? (choose the best three answers)
- A . How many hours did I spend on the project yesterday?
- B . What impediments are in my way or in the way of the team?
- C . Why were you late?
- D . How many meetings did you have yesterday?
- E . What work am I going to do today to help the team achieve its goal?
- F . What work did I do yesterday to help the team achieve its goal?
B,E,F
Explanation:
The Developers can select whatever structure and techniques they want, as long as their Daily Scrum focuses on progress toward the Sprint Goal and produces an actionable plan for the next day of work. This creates focus and improves self-management.
The Developers can use for instance these questions if they want.