Practice Free OMG-OCEB2-FUND100 Exam Online Questions
Which is a recognized perspective covered by Balanced Scorecard?
- A . logistics
- B . financial
- C . management
- D . organization
Which statement about Message Flow in BPMN is true?
- A . Message Flow is drawn as a black line with a solid arrowhead.

- B . Message Flow is drawn as a dotted black line with an open arrow.

- C . Message Flow describes the flow of messages between two Flow Objects within the same pool.
- D . Message Flow describes the flow of messages between two entities that are prepared to send and receive messages.
All Start Events for an Embedded Sub-Process must be of which type?
- A . Signal
- B . Multiple
- C . Message
- D . None
Which is a characteristic of process discovery?
- A . Making organizational understanding of current business processes explicit
- B . Optimizing existing business processes based on simulation of new alternatives
- C . Identifying key business stakeholders and subject matter experts
- D . Transforming existing process definitions into an executable format
Select the list of BPMN Activities:
- A . Task, Process
- B . Task, Sub-Process
- C . Task, Process, Action
- D . Task, Sub-Process, Action
- E . Task, Process, Sub-Process
Which statement is true regarding a black-box Pool?
- A . It indicates a participant.
- B . It can be partitioned using lanes.
- C . It shows full process information.
- D . It cannot be used if messages should be exchanged.
Which organizational entities do the process areas of maturity level 2 of the Business Process Maturity Model (BPMM) focus on?
- A . work units
- B . business area managers
- C . information technology operations
- D . end-to-end product and service offerings
What is the meaning of an Expanded Sub-Process that lacks Sequence Flows between its Tasks?
- A . The Tasks are performed in Top to Bottom and Left to Right order, each Task executed once.
- B . The diagram is flawed: Tasks within a Sub-Process must be connected with Sequence Flows.
- C . The Tasks are performed in any order for any number of times including the possibility of skipping one or more of the Tasks entirely. These Tasks are performed until the Process arbitrarily decides to cease the execution.
- D . Each Task is performed once and only once, the order of execution is not specified, all the Tasks are simultaneously enabled for execution, and the execution of each Task can be contemporaneous with the others.
Refer to the exhibit.

Which is a statement of the goal of the following process?
- A . Designate the unassigned switch with the proper responsibility.
- B . Notify all switches of a pending workload so they can plan their workloads.
- C . Route the incoming request to a switch that has been allocated to a pending project.
- D . Assign the message to the first available switch.
- E . Locate and report information on the status of the incoming tasks to the requesting office.
A bank call center receives a banking customer incoming call for customer support. Upon receiving the call, the help desk staff identifies the reason the customer is calling for assistance. If the call is related to a problem with the Bank’s web site, the customer is transferred to the web site web resolution team. If the call is related to a forgotten or incorrect password or account id, the customer is transferred to the account maintenance group. If the customer would like to modify their existing set of services or add a service, they are transferred to the bank services group.
Which representation correctly depicts these options?


- A . Option A
- B . Option B
- C . Option C
- D . Option D