Practice Free APM-PFQ Exam Online Questions
Question #81
When in the project life cycle might analogous estimating be most commonly used?
- A . Transition.
- B . Concept
- C . Deployment.
- D . Definition.
Question #82
How should issues be prioritised?
- A . The time order in which the issues occurred.
- B . The impact on success criteria and benefits.
- C . The relative seniority of the issue owner.
- D . The relationship with relevant risk.
Question #83
Which is one of the three key project constraints?
- A . Time
- B . Political
- C . Environmental
- D . Technical
Question #84
What is the key benefit of having configuration management in the project?
- A . It allows a thorough assessment of the factors that are most likely to affect the change.
- B . It is means to justify to the customer variances from the original objectives.
- C . It ensures that the delivered product most closely meets the needs of the customer.
- D . It manages the impact of change to the project scope.
Question #85
A review undertaken to decide whether a project should proceed into its next phase is known as a:
- A . gate review.
- B . feasibility study.
- C . milestone review.
- D . evaluation review
Question #86
Which of the following is most true of the business case?
- A . It provides details of the overarching approach to be taken to move the current to a future desirable state using a coordinated and structured approach.
- B . It evaluates the benefit, cost and risk of alternative project options and provides a rationale for the preferred solution.
- C . It demonstrates the relationship between the costs of undertaking a project, initial and recurrent, and the benefits likely to arise from the changed situation, initially and recurrently.
- D . It describes each major element in the work breakdown structure (WBS) describing the work content, resources required, the time frame of the work element and a cost estimate.
Question #87
Which one of the following is the best description of project scope?
- A . Scope is detailed in the business case.
- B . Scope is the total work content of a project.
- C . Scope is an outcome of the scheduling and estimating processes.
- D . Scope defines what is NOT delivered by the project.
Question #88
Establishing success criteria is important at the start of the project, as they:
- A . indicate how the stakeholder needs will be met.
- B . ensure adequate resource allocation.
- C . indicate what is important in supplier selection.
- D . ensure comprehensive risk analysis.
Question #89
The combination of which two structures creates the responsibility assignment matrix (RAM)?
- A . OBS and CBS.
- B . OBS and WBS.
- C . PBS and CBS.
- D . WBS and CBS.
Question #90
A project is typically defined in terms of scope, time, cost and which other parameter?
- A . Benefits.
- B . Quality.
- C . Tolerance.
- D . Controls.