Once a change has been requested what is the next step in the change control process?
- A . Evaluate the change.
- B . Advise the sponsor.
- C . Update the change log.
- D . Update the project plan.
The main aim of a project risk management process should be to:
- A . identify project risks and then manage them appropriately.
- B . identify all project risks and transfer them immediately.
- C . identify all the things that are threats or opportunities on a project.
- D . satisfy the organisation’s project management process.
Suppliers are stakeholders of a project management plan because they:
- A . contribute to the project’s procurement strategy.
- B . help satisfy the project’s resource requirements.
- C . provide acceptance certificates based on quality of resources supplied.
- D . determine the quality requirements of goods supplied.
Which activity is not utilised by scope management?
- A . Defining.
- B . Identifying.
- C . Delivering.
- D . Controlling.
One difference between a project and business as usual is:
- A . projects achieve specified benefits but business as usual has only vague benefits.
- B . projects drive change whereas business as usual continues existing activities.
- C . projects have tightly controlled budgets whereas business as usual does not.
- D . projects have unclear deadlines but business as usual has multiple milestones
If using an iterative life cycle what actions might be necessary for scope items that are NOT considered as ‘must have’?
- A . They need to be given a special priority to ensure that they are definitely delivered.
- B . They should have best resort to ensure they efficiently delivered.
- C . The project could be If the delivery of these requirements were proving more difficult than expected
- D . They would sacrificed if at any time Was to go over budget or be late
To develop and establish a proper communication plan within a project, the project manager needs to consider which type of analysis?
- A . Budget.
- B . Stakeholder.
- C . Resource.
- D . Schedule
Who is primarily responsible for ensuring the implementation of formal change control?
- A . Key stakeholders.
- B . The Project Manager.
- C . The project sponsor.
- D . The project team.
Which one of the following would best describe a post project review?
- A . It is a personal appraisal for each team member on completion Of the project.
- B . It appraises the products of the project.
- C . It considers all aspects of the management of the project.
- D . It involves only the project implementation team.
Estimating by using historical information is known as:
- A . comparative estimating.
- B . parametric estimating.
- C . bottom-up estimating.
- D . strategic estimating.