Question #71
What is a factor that is important when communicating as part of stakeholder engagement?
- A . Planned communication will help to establish the level of interest and power a stakeholder is likely to possess.
- B . Planned communication will increase the number of stakeholders who are likely to have an interest in the project.
- C . Planned communication will reduce the power of stakeholders who are likely to have an interest in the project.
- D . Planned communication is likely to reduce the number Of valid stakeholders who have an interest in the project.
Question #72
One of the main purposes of dividing a project into life cycle phases is to:
- A . break the work into controllable blocks in terms of effort and size.
- B . ensure the processes are properly maintained.
- C . ensure that the workforce is certain of their individual roles.
- D . provide a means Of producing overall project cost estimates.
Question #73
Which one of the following statements best describes the use of an issue log?
- A . summary of all possible alternative resolutions of an issue.
- B . summary of all the project issues, their analysis and status.
- C . tool to ensure that a process is in place for capturing all issues.
- D . tool to ensure that the issue management process is adhered to.
Question #74
What is meant by the term programme management?
- A . The management of group of projects or activities that have a common business aim.
- B . The line management of team of programme managers.
- C . The management of functional are aused by a number of different projects.
- D . The management of the programme of activities identified in the project plan
Question #75
Which of the following disadvantages applies to video conferencing?
- A . A level of technological expertise is required.
- B . Body language can reinforce the message.
- C . It is harder to maintain concentration.
- D . There are increased costs of getting to the meeting.
Question #76
Which of the following is not an output of a critical path analysis?
- A . Total and free float.
- B . Earliest start time and latest finish time of activities.
- C . Project completion time.
- D . Cost-benefit analysis.
Question #77
Which of the following would be a benefit to an organization of effective project management?
- A . Significant cost savings in the organization’s business as usual activities.
- B . Guaranteed increased profitability and market share from successful projects.
- C . Use of resources and greater likelihood of achieving a successful project.
- D . Having qualified and trained project managers in the organization.
Question #78
Why is it important to produce a project management plan?
- A . It shows the benefits expected at the close of the project and the specific stakeholders who are involved.
- B . It provides justification for undertaking the project and provides a rationale for the preferred solution.
- C . It sets and clarifies the expectations of all stakeholders who are involved in the project delivery.
- D . It identifies and establishes the most appropriate means of procuring the component parts or services for the project being delivered.
Question #79
How is the deployment baseline used throughout the project?
- A . Progress monitoring and implementation of change control.
- B . Benefits realisation.
- C . Identify options for deployment.
- D . Prepare users for delivery of the output into operation.
Question #80
Which of the following is a part of change control?
- A . Requests for change are realised.
- B . Requests for change are mitigated.
- C . Requests for change are evaluated.