Practice Free APM-PFQ Exam Online Questions
The primary purpose of the post-project review is to:
- A . find out who was responsible for problems on the project and why.
- B . find out whether the business benefits were achieved and why.
- C . find out who performed well on the project in order to support future resource allocations.
- D . identify lessons learned to enable continuous improvement.
What is one of the main features of using analogous method of estimating?
- A . The individual group members use a statistical relationship between historic data and other variables to calculate an estimate.
- B . The task of producing the estimates will be delegated to those who are actually going to deliver the individual pieces of work or work packages.
- C . The individual group members, who are tasked with providing the estimates, do this in isolation from each other.
- D . The individual group members identify a previously delivered project of the same size. complexity and delivery method.
One of the reasons a project life cycle is split into phases is to:
- A . facilitate formal go/no-go decision making during the project.
- B . balance the costs of work in each phase of project development.
- C . mirror the major deployments of resources throughout the project.
- D . chunk work into time periods of similar durations.
What is a likely benefit of re-estimating throughout the project life cycle?
- A . The project will be much more economically viable.
- B . The business case is justified to a greater degree.
- C . Overall project duration is reduced.
- D . Reduction in contingency reserves are achieved.
Which of the following are phases in an iterative project life cycle?
1) Concept
2) Feasibility
3) Deployment
4) Development
- A . 3 and 4 only
- B . 1, 2 and 3
- C . 1 and 2 only
- D . 2, 3 and 4
Which one of the following best describes project sponsorship?
- A . Project sponsorship is the customer’s role responsible for identifying the business need.
- B . Project sponsorship is an active, senior management role responsible for identifying the business need, problem or opportunity.
- C . Project sponsorship is an active, senior management role managing the customer’s needs subject to an agreed cost.
- D . Project sponsorship is the project manager’s role responsible for delivering the business need and addressing any problems or opportunities.
How are outputs best described?
- A . The changed circumstances or behavior that results from their use.
- B . The work packages developed in the W BS for the project.
- C . The realisation of benefits at the end Of the project.
- D . The tangible or intangible products typically delivered by a project.
At which stage, in the Tuckman team development model, are team members clear and comfortable with their roles and responsibilities, and the project manager starts to see signs of the team working together?
- A . Storming.
- B . Forming.
- C . Norming.
- D . Performing
At which stage, in the Tuckman team development model, are team members clear and comfortable with their roles and responsibilities, and the project manager starts to see signs of the team working together?
- A . Storming.
- B . Forming.
- C . Norming.
- D . Performing
While carrying out quality management for the project, you have been assigned the task of determining the quality standards that are applicable and how they should apply.
Which part of quality management would best describe this activity?
- A . Quality planning.
- B . Quality assurance.
- C . Total quality.
- D . Quality control.