What is the likely decision to arise from the response stage of the risk management process?
- A . Whether to proceed with the project or recommend termination.
- B . Whether the process being used is robust enough for the project being undertaken.
- C . Whether to proactively invest to bring the exposure to risk within tolerable levels.
- D . Whether to use brainstorming or a workshop to decide on the best response.
Which of the following is true regarding differences between linear and iterative life cycles?
- A . A linear life cycle is best for evolving projects whereas an iterative life cycle is better for more structured projects.
- B . A linear life cycle is sequential whereas an iterative life cycle repeats one or more phases.
- C . A linear life cycle is always longer in duration whereas an iterative life cycle is always shorter in its duration.
- D . A linear life cycle is formally managed by dedicated project manager whereas management responsibility is shared in an iterative life cycle
Which of the following defines the term ‘deployment baseline’?
- A . The starting point for creating a resource histogram.
- B . The basis for creating an organisational breakdown structure.
- C . The starting point for the monitoring of project risks.
- D . The basis for progress monitoring.
The purpose of project progress reporting is to:
- A . ensure a simpler critical path.
- B . enable the tracking of project deliverables.
- C . ensure stakeholder acceptance of project deliverables.
- D . provide an increased total float.
One advantage of virtual communications is:
- A . that nonverbal signals can have an impact on discussions.
- B . it’s easy to detect signs of conflict within the project team.
- C . access to a wider resource pool for the project.
- D . that the project team will always be co-located.
What aspects of benefits realisation would be considered as most important to note in the business case?
- A . Who is going to be responsible for carrying out each of the projects activities.
- B . How the benefits will be realised, measured and the stakeholders involved
- C . What type of contract is going to be used to procure delivery of the project.
- D . Which benefits should be realised first and then the subsequent order
What role does the project manager have in the writing of the business case? The project manager:
- A . works with the project sponsor.
- B . has no involvement.
- C . must develop it themself.
- D . works with the end user.
What would be a most likely result for an organisation following a PESTLE analysis?
- A . The organisation would know what political change is most likely and therefore the impacts on objectives considered.
- B . The organisation would most likely have a number of options available as to how the desired objectives could be achieved.
- C . The organisation would have an understanding of the necessary skills required to deliver the objectives required.
- D . The organisation would be able to develop an accurate estimate of the costs and time frame for the objectives to be achieved.
What would be a most likely result for an organisation following a PESTLE analysis?
- A . The organisation would know what political change is most likely and therefore the impacts on objectives considered.
- B . The organisation would most likely have a number of options available as to how the desired objectives could be achieved.
- C . The organisation would have an understanding of the necessary skills required to deliver the objectives required.
- D . The organisation would be able to develop an accurate estimate of the costs and time frame for the objectives to be achieved.
Which statement regarding the purpose of the business case would be the most true?
- A . Once agreed the business case will become the baseline by which the project will be deployed,
- B . It will act as a reference for the project team regarding the specific. processes to be used for project delivery.
- C . It will determine which stakeholders are most eligible to become members of the steering group,
- D . It will be referred to throughout the project in order to make decisions about the continuing viability of the project.