Question #121
Which type of projects needs to consider environmental constraints?
- A . Construction projects only.
- B . Construction and petrochemical projects only.
- C . All but IT projects.
- D . All projects.
Question #122
The accuracy of an estimate should:
- A . decrease as a project progresses through its lifecycle.
- B . increase as a project progresses through its lifecycle.
- C . stay constant throughout the project.
- D . vary independently of where the project is in its lifecycle
Question #123
Which one of the following is NOT a project change?
- A . An approved omission from the agreed project scope.
- B . The potential for agreed resources to be removed from the project.
- C . requirement for extra expenditure to cover increased supplier costs.
- D . The removal of work packages from the agreed project scope.
Question #124
Which of the following are not considered by quality planning?
- A . Contingency budget for remedial work.
- B . Equipment required for quality testing.
- C . Staff qualified to undertake inspections.
- D . Processes to obtain stakeholder approvals.
Question #125
Which of the following is an activity in a typical configuration management process?
- A . Evaluation.
- B . Identification.
- C . Registration.
- D . Justification.
Question #126
Key performance indicators (KPIs) are used for measuring how a project is progressing towards success and are monitored by project managers:
- A . at the post-project review.
- B . not more frequently than monthly.
- C . throughout the project.
- D . only when assessing project risk.