Question #160
Which plan is used to organize and control the work when executing a work package?
- A . team plan
- B . A stage plan
- C . A project plan,
- D . An exception plan
Correct Answer: A
A
Explanation:
When executing a Work Package, the Team Plan is used to organize and control the work. The Team Plan is derived from the Stage Plan and provides detailed allocations and explanations of how the team will deliver the work package assigned to them. It focuses specifically on the tasks and resources at the team level, detailing the schedule and resources needed to complete the work.
Reference: (PRINCE2® 7 Foundation Handbook, AXELOS)
A
Explanation:
When executing a Work Package, the Team Plan is used to organize and control the work. The Team Plan is derived from the Stage Plan and provides detailed allocations and explanations of how the team will deliver the work package assigned to them. It focuses specifically on the tasks and resources at the team level, detailing the schedule and resources needed to complete the work.
Reference: (PRINCE2® 7 Foundation Handbook, AXELOS)
Question #162
When does the ‘directing a project’ process start?
- A . When the project manager submits the project brief for approval
- B . When the request to authorize a project is received
- C . After the project has been authorized by the business layer
- D . After the project mandate has been received
Correct Answer: B
B
Explanation:
The ‘Directing a Project’ process in PRINCE2 starts when the request to authorize a project is received. This request usually comes after the initial project setup has been reviewed and there is a need to formally authorize the project to begin detailed planning and execution. This is a crucial step in establishing the governance framework that will guide the project’s overall direction.
Reference: (PRINCE2® 7 Foundation Handbook, AXELOS)
B
Explanation:
The ‘Directing a Project’ process in PRINCE2 starts when the request to authorize a project is received. This request usually comes after the initial project setup has been reviewed and there is a need to formally authorize the project to begin detailed planning and execution. This is a crucial step in establishing the governance framework that will guide the project’s overall direction.
Reference: (PRINCE2® 7 Foundation Handbook, AXELOS)
Question #162
When does the ‘directing a project’ process start?
- A . When the project manager submits the project brief for approval
- B . When the request to authorize a project is received
- C . After the project has been authorized by the business layer
- D . After the project mandate has been received
Correct Answer: B
B
Explanation:
The ‘Directing a Project’ process in PRINCE2 starts when the request to authorize a project is received. This request usually comes after the initial project setup has been reviewed and there is a need to formally authorize the project to begin detailed planning and execution. This is a crucial step in establishing the governance framework that will guide the project’s overall direction.
Reference: (PRINCE2® 7 Foundation Handbook, AXELOS)
B
Explanation:
The ‘Directing a Project’ process in PRINCE2 starts when the request to authorize a project is received. This request usually comes after the initial project setup has been reviewed and there is a need to formally authorize the project to begin detailed planning and execution. This is a crucial step in establishing the governance framework that will guide the project’s overall direction.
Reference: (PRINCE2® 7 Foundation Handbook, AXELOS)
Question #164
What 15the purpose of the ‘progress! practice?
- A . To review whether the use of the products is likely to lead to the expected benefits
- B . To define the roles and responsibilities for monitoring progress
- C . To measure actual achievements against the planned time and cost targets for the project
- D . To control events that could have a positive or negative effect on project objectives
Correct Answer: C
C
Explanation:
The purpose of the ‘Progress’ practice in PRINCE2® is to provide a mechanism to monitor and
compare the actual project progress against the planned objectives, particularly in terms of time and cost. This monitoring helps in identifying any deviations from the plan and facilitates timely corrective actions to keep the project on track.
Reference: = PRINCE2® 7 Foundation Training Manual and official PRINCE2® website documentation
C
Explanation:
The purpose of the ‘Progress’ practice in PRINCE2® is to provide a mechanism to monitor and
compare the actual project progress against the planned objectives, particularly in terms of time and cost. This monitoring helps in identifying any deviations from the plan and facilitates timely corrective actions to keep the project on track.
Reference: = PRINCE2® 7 Foundation Training Manual and official PRINCE2® website documentation
Question #164
What 15the purpose of the ‘progress! practice?
- A . To review whether the use of the products is likely to lead to the expected benefits
- B . To define the roles and responsibilities for monitoring progress
- C . To measure actual achievements against the planned time and cost targets for the project
- D . To control events that could have a positive or negative effect on project objectives
Correct Answer: C
C
Explanation:
The purpose of the ‘Progress’ practice in PRINCE2® is to provide a mechanism to monitor and
compare the actual project progress against the planned objectives, particularly in terms of time and cost. This monitoring helps in identifying any deviations from the plan and facilitates timely corrective actions to keep the project on track.
Reference: = PRINCE2® 7 Foundation Training Manual and official PRINCE2® website documentation
C
Explanation:
The purpose of the ‘Progress’ practice in PRINCE2® is to provide a mechanism to monitor and
compare the actual project progress against the planned objectives, particularly in terms of time and cost. This monitoring helps in identifying any deviations from the plan and facilitates timely corrective actions to keep the project on track.
Reference: = PRINCE2® 7 Foundation Training Manual and official PRINCE2® website documentation