Practice Free PK0-005 Exam Online Questions
Which of the following communication methods would be the most appropriate to finalize the handoff of deliverables?
- A . A virtual meeting with all the stakeholders
- B . A face-to-face kickoff meeting with the stakeholders
- C . A closure meeting with the project team and stakeholders
- D . A final report submitted via email to the stakeholders
Which of the following is a reason to use a SOW on a project?
- A . To find out the contact information for the vendors
- B . To review the list of stakeholders
- C . To ensure the team stays within the scope of the contract
- D . To give explicit instruction on how to execute the work
A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change.
Which of the following is the sequence of these events?
- A . Issue, issue
- B . Issue, risk
- C . Risk, issue
- D . Risk, risk
A team is working on a project that has different stages, such as initiation, planning, execution, and closure.
Which of the following is this an example of?
- A . Agile
- B . Waterfall
- C . Standard
- D . Hybrid
During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately.
Which of the following is best for determining this information?
- A . PERT chart
- B . Milestone chart
- C . Gantt chart
- D . Budget burndown chart
During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department.
Which of the following should the project manager do to increase project certainty?
- A . Hold a new backlog prioritization meeting.
- B . Add milestones to check the project’s progress.
- C . Adjust the task relationship to complete coding in advance.
- D . Apply contingency buffers to the critical path.
A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to identify the level of engagement among project team members.
Which of the following would be the best tool for the project manager to use?
- A . Meeting chat
- B . Email
- C . Real-time survey
- D . Whiteboard
A project manager submits a change request. The change request is rejected because of code freeze.
Which of the following actions should the project manager take next?
- A . Update the risk register.
- B . Escalate the issue for exceptional approval.
- C . Communicate to the stakeholders.
- D . Submit a duplicate change request.
Which of the following demonstrates awareness of regulations and standards when conducting a project?
- A . Establishing a measurement system for the team members’ performance
- B . Controlling project costs to fall within the company-approved variance
- C . Reviewing advertising trends in the market before launching a new product
- D . Submitting architectural plans for approval before commencing construction
Government projects require that personnel submit to background screenings for certain clearance requirements.
Which of the following best describes this process?
- A . Data security
- B . Operational security
- C . Physical security
- D . Digital security