Practice Free PK0-005 Exam Online Questions
During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts.
Which of the following should the team use?
A)
B)
C)
D)
- A . Option A
- B . Option B
- C . Option C
- D . Option D
A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor.
Which of the following is the first document the PM should update?
- A . Project network diagram
- B . Gantt chart
- C . Issue log
- D . Risk report
Which of the following would be considered operational security?
- A . Mobile device compliance
- B . Background screening
- C . Multifactor authentication
- D . Facility access
A project manager decided to host the development environment on a cloud service.
Which of the following would the project manager most likely use for this purpose?
- A . IaaS
- B . XaaS
- C . DaaS
- D . SaaS
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter.
Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
- A . Compromising
- B . Forcing
- C . Smoothing
- D . Collaborating
A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance.
Which of the following is the project manager most likely conducting?
- A . Application deployment
- B . Rollback plans
- C . Validation checks
- D . Maintenance window schedules
Which of the following is the best example of a breach of physical security?
- A . System user IDs being used by multiple individuals
- B . Printers that do not request user authentication
- C . Developers having full access to both development and production environments
- D . Project documentation that is only kept on a removable device
Two stakeholders, who have a history of animosity toward one another, are in disagreement during a
project. The project’s timeline depends on the stakeholders accomplishing their tasks.
Which of the following conflict resolution methods would be best to utilize?
- A . Smoothing
- B . Confronting
- C . Forcing
- D . Compromising
A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps.
Which of the following actions should the project manager take?
- A . Notify customers the downtime will take longer than expected.
- B . Add new team members to help speed up validation.
- C . Begin executing the rollback plan.
- D . Record the issue and proceed with the implementation.
A project manager realizes that a project will not be completed on time due to resource constraints.
Which of the following actions should the project manager take NEXT?
- A . Trigger the contingency plan and communicate with the stakeholders.
- B . Work with the functional managers to create a work-around.
- C . Submit a change request to the change control board.
- D . Transfer the risk by hiring a new vendor who was successful on a previous project.
- E . Set up an escalation meeting with the sponsor.