A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports.
Which of the following cloud models would the company suggest to the global franchise?
- A . laaS
- B . XaaS
- C . PaaS
- D . SaaS
A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85.
Which of the following can the project manager infer about the current project status?
- A . The project is ahead of schedule and under budget.
- B . The project is behind schedule and over budget
- C . The project is ahead of schedule and over budget.
- D . The project is behind schedule and under budget
Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day.
Which of the following techniques is the project manager using?
- A . Avoiding
- B . Smoothing
- C . Forcing
- D . Compromising
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project.
Which of the following tools will the project manager MOST likely use?
- A . Dashboard
- B . Gantt chart
- C . Work breakdown structure
- D . Requirements Traceability Matrix
Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written.
Which of the following relationships best describes this scenario?
- A . Start-to-start
- B . Start-to-finish
- C . Finish-to-finish
- D . Finish-to-start
Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project.
Which of the following should the project manager MOST likely do to move forward?
- A . Communicate with the affected stakeholders.
- B . Initiate a formal change request to modify the cost
- C . Adjust the scope to stay within the cost.
- D . Set a new cost using a lightweight estimation method.
A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed.
Which of the following would clarify what the project implementation partner was contractually expected to complete?
- A . SOW
- B . RFI
- C . RFQ
- D . WBS
A project team has just experienced an unexpected event and implemented a work-around.
Which of the following documents should be used to record the event? (Select TWO).
- A . Risk report
- B . Defect log
- C . Issue log
- D . Backlog
- E . Change log
- F . Progress report
A PM is working on the schedule for a project that has technical tasks and requires a SME’s knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates.
Which of the following is the best tool to track this data?
- A . Gantt chart
- B . Project organization chart
- C . Program Evaluation Review Technique chart
- D . Milestone chart
A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings.
Which of the following types of communication is the sponsor using?
- A . Informal communication
- B . Formal communication
- C . Synchronous communication
- D . Asynchronous communication