Practice Free PK0-005 Exam Online Questions
During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties.
Which of the following documents would the PM most likely create?
- A . Business requirement
- B . Client statement of work
- C . Formal contract
- D . Project charter
A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication.
The project manager should update the stakeholder register with:
- A . the preferred sponsor’s communication channel.
- B . the preferred project manager’s communication channel.
- C . the preferred reported communication channel.
- D . email communication as the preferred communication channel.
As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations.
Which of the following should the project manager do? (Select two).
- A . Purchase the materials.
- B . Assign the resources.
- C . Accept delays in the work.
- D . Approve the deliverables.
- E . Monitor the performance.
- F . Negotiate with the vendors.
A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager.
Which of the following should the project manager do first to prevent this situation from reoccurring?
- A . Meet with the team and highlight the importance of change management.
- B . Roll back the process and submit a change request.
- C . Document the event as a lesson learned.
- D . Remove the team member who bypassed the CCB process.
Which of the to and allowing interactive feedback from a project team?
- A . Text message
- B . Chat
- C . Email
- D . Videoconference
Which of the following is a quantitative key performance indicator?
- A . The project sponsor ranked the graphics of an application as four out of five.
- B . The project implements the application in ten different geographical regions.
- C . The workers complete tasks on average 25% faster using a new application.
- D . The use of a multimedia interface appeals more to users under the age of 21.
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project.
Which of the following best describes this activity?
- A . Key stakeholder identification
- B . Preliminary procurement
- C . Solution design determination
- D . Critical factor enlistment
A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase.
Which of the following types of testing should be done?
- A . Performance
- B . Smoke
- C . Regression
- D . Unit
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects.
Which of the following tools should the project team use to find the cause?
- A . Kanban board
- B . Pareto chart
- C . Ishikawa diagram
- D . Decision tree
A customer requests some changes to a product, and those changes are approved by the CCB.
Which of the following should be changed first?
- A . ROI
- B . KPI
- C . RACI
- D . SOW