Practice Free PK0-005 Exam Online Questions
Question #111
A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process.
Which of the following techniques is the project manager using?
- A . Forcing
- B . Avoiding
- C . Compromising
- D . Smoothing
Question #112
A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time.
Which of the following should the project manager do next?
- A . Request a change control ticket.
- B . Review the schedule plan.
- C . Refine the project documentation.
- D . Revise the communication plan.