Practice Free PK0-005 Exam Online Questions
A new project has been assigned to a project manager.
In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
- A . Lead architect
- B . Project sponsor
- C . Program manager
- D . Scrum master
During an active project, the finished product is not meeting quality specifications.
Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?
- A . Communicate the change status.
- B . Document change recommendations
- C . Create a change request.
- D . Implement the changes
During an active project, the finished product is not meeting quality specifications.
Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?
- A . Communicate the change status.
- B . Document change recommendations
- C . Create a change request.
- D . Implement the changes
Which of the following tasks should the project manager complete first when validating deliverables?
- A . Assess the documentation.
- B . Obtain stakeholder feedback.
- C . Review the project objectives.
- D . Mitigate risks.
A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs.
Which of the following represents the total amount that should be budgeted for the task?
- A . 9 days and $3,000
- B . 10 days and $3,200
- C . 12 days and $3,800
- D . 14 days and $4,000
Project stakeholders have asked the team to use Scrum to run a software implementation project.
Which of the following is most likely to take place during a Scrum ceremony?
- A . Reviewing project blockers
- B . Defining roles and responsibilities
- C . Establishing a project schedule
- D . Determining a project budget
While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises.
Which of the following should the facilitator do to overcome the challenges?
- A . Instruct the team members to set their speakers to maximum volume and mute their microphones.
- B . Require everyone to turn on their cameras and use the same background filter.
- C . Encourage the use of the chat and use plain language when speaking.
- D . Allow one person to speak at a time after receiving acknowledgment from the facilitator.
An existing application that is highly utilized by clients is moving to a new release.
Which of the following environments contains this application?
- A . Development
- B . Production
- C . Testing
- D . QA
A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project.
Which of the following should the project manager do?
- A . Collate the lessons learned.
- B . Perform a gap analysis.
- C . Review existing artifacts.
- D . Conduct a retrospective.
A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California.
Which of the following is most important for the project manager to consider when setting up the session?
- A . Cultural differences
- B . Technological factors
- C . Time zones
- D . Language barriers