Practice Free CBAP Exam Online Questions
Which of the following types of elicitation allows each stakeholder to freely discuss their role in a particular process?
- A . Focus group
- B . Structured interview
- C . Quick Interview
- D . Unstructured interview
A business analyst (BA) is assigned to a project which has two main stakeholders: a highly regulated government agency and a less formal private company. To select the business analysis approach, the BA mi! conduct a meeting with representatives from each entity to decide on the level of formally needed for requirements and design specifications. During
the meeting, what should the BA’s strategy be?
- A . Develop consensus on a tailored approach for formality
- B . Use a formal approach to appeal to the government entity’s higher authority
- C . Employ the standard business analysis level of formality
- D . Ask the government entity to accept a flexible collaborative approach
A business analyst (BA) is preparing to specify requirements. Various attributes can be specified for each requirement or set of requirements.
Which approach contains a suitable set of attributes?
- A . Stakeholder Engagement
- B . Information Management
- C . Business Analysis
- D . Governance
C
Explanation:
Reference: IIBA BABOKv3 (149)
Nancy has asked you to trace a particular requirement for her.
What does ‘to trace a requirement’ mean?
- A . Tracing a requirement means to look at a requirement and the others to which it is related. It links risk,
cost, quality, and scope elements to stakeholder and solution requirements to other artifacts created by the team and to solution components. - B . Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to stakeholder and solution requirements to other artifacts created by the team and to solution components.
- C . Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to components in the project’s work breakdown structure.
- D . Tracing a requirement means to track a requirements from its first identification all the way to its completion to see what issues, risks, costs, quality, and defects have surrounded the requirement
You are the business analyst for your organization. Management realizes that a proposed solution has risks that may cause the entire project to fail. They would like you to prioritize the requirements with maximum risks first so that if the project fails, there is little loss of capital in the project implementation.
What requirements prioritization approach is management asking you to create in this instance?
- A . Implementation difficulty
- B . Business or technical risk
- C . Likelihood of success
- D . Relationship to other requirements