Practice Free CBAP Exam Online Questions
What does the T in SWOT analysis mean?
- A . Trial
- B . Threats
- C . Test
- D . Time
As part of identifying an enterprise’s capability to adopt a potential solution, a business analyst (BA) is reviewing existing processes and tools within the enterprise for their ability to adapt to a new solution.
Which of the following assessments is the BA performing?
- A . Stakeholder
- B . Enterprise
- C . Organizational
- D . Operational
B
Explanation:
Reference: IIBA BABOKv3 (166)
You have identified several stakeholders that you believe are kinesthetic learners.
Which statement best describes the kinesthetic learning approach?
- A . The learners learn best by reading and pondering.
- B . The learners learn best be experiencing the topic.
- C . The learners learn best by seeing the topic in a model or through storyboards.
- D . The learners are not interested in the topic unless they can immediately apply it to their lives or jobs.
You have identified several stakeholders that you believe are kinesthetic learners.
Which statement best describes the kinesthetic learning approach?
- A . The learners learn best by reading and pondering.
- B . The learners learn best be experiencing the topic.
- C . The learners learn best by seeing the topic in a model or through storyboards.
- D . The learners are not interested in the topic unless they can immediately apply it to their lives or jobs.
A business analyst (BA) is working on a payment system (PS) implementation. A set of systems which should interact with a new system has been identified. The business analyst defined that a user with role of "Supervisor" in the PS must pass a two-factor authentication before an execution of the functions: "Change system parameters" and "Set up new supervisor." A user must have the role of "Supervisor" to use the standard functions "Send mail notification" or "Send SMS notification".
The BA defined the following use cases:
• "Change system parameters"
• "Setup new supervisor"
• "Send mail notification"
• "Send SMS notification"
• "Send notification"
• "Pass a two-factor authentication"
The BA wants to create a Use Case diagram.
What standard relationship should be defined between "Change system parameters", "Setup new supervisor" and "Pass a two-factor authentication"?


- A . Option A
- B . Option B
- C . Option C
- D . Option D
Which of the following is the process of analyzing the areas of a project that are most affected by risk?
- A . Risk Identification
- B . Risk Urgency Assessment
- C . Risk Categorization
- D . Risk Analysis
You are the business analyst for a solution that has 435 stakeholders.
How many communication channels exist in this project?
- A . 188,790
- B . 189,225
- C . 94,395
- D . 435
You are the business analyst for your organization and are working on prioritizing requirements.
What plan should guide you through this process?
- A . Risk management plan
- B . Project management plan
- C . Requirements management plan
- D . Scope management plan
A national branch of a global company is struggling to improve business processes of its Public and Government Affairs (PGA) department. To work with external stakeholders effectively, PGA employees need to collect, manage, and exchange a vast amount of information. Complex cases involve collaboration of many employees from different departments. The ability to share information and to coordinate corresponding activities is crucial for the company’s growth plans. Their current tools and practices do not serve the purpose well. The existing system, which was deployed a couple of years ago, has only a few active users. The majority of PGA employees avoid using it because the system is hard to use and lacks needed functionality. Consequently, available information is mostly unstructured and stored either locally or on a shared network drive. Some of the information exists only in a paper form.
The branch’s PGA head, who sponsors the project, wants to implement a configurable solution that two other branches successfully deployed several months ago. Both deployments were done by three solution consultants, who will be available to assist in the project. They will be responsible for tailoring the solution to PGA needs, as well as for training the PGA staff. With their help, the sponsor plans to complete the project in approximately three months.
The solution consultants reside in another country 7 hours ahead of the rest of the project team. They will be available part-time, but are planning two one-week long trips to the PGA central office to conduct initial training and to participate in the final deployment of the system into production. The consultants, in turn, expect a business analyst (BA) to assist in collecting necessary data and defining customization requirements.
What should define the timing of business analysis work in this project?
- A . Buy-in of the proposed solution
- B . Approach used by the previous deployments
- C . Availability of solution consultants
- D . Overall project schedule
A project is implemented using a predictive approach. Unfortunately, a lot of change requests (CR) have been raised. A project manager (PM), who should approve each change request, is overworked.
What could the business analyst (BA) propose to make things better?
- A . Approve the CRs independently for the PM
- B . Transfer responsibility from the PM to a project’s sponsor
- C . Revisit the Business Analysis Governance approach
- D . Decline CRs because of the approach