Practice Free C_TS422_2504 Exam Online Questions
In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning.
What does this mean for the capacity requirements of a new order?
- A . MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.
- B . MRP creates the capacity requirements without considering existing load on the work centers.
- C . MRP creates the capacity requirements at the earliest possible time.
- D . MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.
What is a work center hierarchy?
- A . A group of alternative work centers for production structured in hierarchy levels by priorities
- B . A group of alternative work centers providing a cumulative available capacity for production
- C . A group of work centers in a production line being used in sequence for production
- D . A group of work centers in a parallel sequence that is used to split production quantities work on them in parallel
In your plant MRP is activated.
Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.
- A . Use a specific MRP list.
- B . Use a specific material status.
- C . Use a specific material group.
- D . Use a specific MRP type.
You are a consultant on an SAP S/4HANA Cloud Greenfield project.
Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.
- A . Efficiency
- B . Accuracy
- C . Timeliness
- D . Stability
Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.
- A . Production cost collector
- B . Production version
- C . Repetitive manufacturing profile
- D . Routing
What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.
- A . Planned order
- B . Scheduling agreement schedule line
- C . Production order
- D . Purchase order
You are trying to create a production order NO valid production version can be selected.
What could be the reasons? Note: There are 2 correct answers to this question.
- A . The order lot size is NOT within the validity range of a production version.
- B . NO production lines are assigned to the production versions.
- C . All production versions for the material are locked.
- D . NO bills of material (BOMs) are assigned to the production versions.
In the context of the capacity scheduling table, how do you define a pacemaker work center?
- A . By assigning it to the first operation of a routing
- B . By assigning it to the production version
- C . By assigning it to the bottleneck operation
- D . By assigning it to the capacity scheduling table
What could be the reason for different combinations of components in a multiple bill of material (BOM)? Note: There are 2 correct answers to this question.
- A . Manufacturing date
- B . BOM header status
- C . BOM component status
- D . Lot size
What will happen in the MRP run if you have created a new MRPrelevant material that supports both inhouse production external procurement?
- A . The MRP run assumes external procurement.
- B . The MRP run assumes inhouse production.
- C . The MRP run plans the material only if a quotation has been maintained.
- D . The MRP run does NOT consider the material; it has to be planned interactively.