Question #31
What is the purpose of an exclusion zone in pipeline construction?
- A . To demarcate the construction site
- B . To establish a safe work area
- C . To mark the location of a pipeline anomaly
- D . To identify the route of the pipeline
Correct Answer: B
Question #32
Who is considered a contractor in pipeline facility construction?
- A . Pipeline operator
- B . Regulatory agency
- C . Inspection service company
- D . Equipment supplier
Correct Answer: C
Question #33
What is the main goal of ANSI Z49.1 regarding property protection?
- A . Preventing welding accidents
- B . Ensuring efficient welding processes
- C . Protecting equipment from damage
- D . Protecting property from fire and explosions
Correct Answer: D
Question #34
What is the primary goal of preliminary alignment?
- A . To achieve final alignment
- B . To ensure machinery stability
- C . To determine equipment classification
- D . To measure piping-imposed strains
Correct Answer: A
Question #35
Which factor necessitates the design of electrical installations to prevent accidental ignition of flammable liquids and gases in petroleum facilities?
- A . Elevated pressures
- B . High temperatures
- C . Chemical changes
- D . All of the above
Correct Answer: D
Question #36
What does “AUT” stand for in API 1104?
- A . Automated Ultrasonic Testing
- B . Arc Welding Technique
- C . Automated Underwater Testing
- D . Arc Ultrasonic Testing
Correct Answer: A