Practice Free API-1184 Exam Online Questions
Question #1
What is the purpose of a warm-up line in machinery?
- A . To regulate machinery speed
- B . To heat up machinery components
- C . To measure machinery vibrations
- D . To control equipment classification
Correct Answer: B
Question #2
What is an “appurtenance” in the context of API RP 1110?
- A . A type of anomaly in the pipeline material
- B . A component attached to the pipeline
- C . A type of pipeline operating condition
- D . A pressure testing tool
Correct Answer: B
Question #3
What is the role of the user-designated machinery representative?
- A . To provide equipment to the vendor
- B . To speak on behalf of the equipment manufacturer
- C . To ensure proper machinery installation decisions
- D . To conduct equipment classification inspections
Correct Answer: C
Question #4
What does API RP 1110 provide guidelines for?
- A . Pressure testing water pipelines
- B . Pressure testing steel pipelines
- C . Pressure testing pipelines for natural gas only
- D . Pressure testing pipelines for liquids only
Correct Answer: B
Question #5
What is the purpose of corrective action in pipeline construction?
- A . To prevent the discovery of nonconformances
- B . To eliminate the cause of a nonconformance and prevent recurrence
- C . To increase the production speed
- D . To change the design of the pipeline facility
Correct Answer: B
Question #6
When should conflicts between API 686 and manufacturers’ procedures be resolved?
- A . Before starting the installation process
- B . After the machinery has been installed
- C . During the precommissioning phase
- D . After the equipment user takes ownership
Correct Answer: A
Question #7
What does “BT” stand for in API 1104?
- A . Butt Welding Technique
- B . Burn-Through
- C . Branch Welding Type
- D . Back Weld Test
Correct Answer: B
Question #8
Which approach involves using intrinsically safe devices and wiring methods to ensure safety in classified locations?
- A . Oil immersion
- B . Nonincendive installations
- C . Positive-pressure ventilation
- D . Intrinsically safe installations
Correct Answer: D
Question #9
Which pressure test type is used to verify the structural integrity of pipelines with time-dependent anomalies?
- A . Qualifying Test
- B . Spike Test
- C . High Pressure Test
- D . Leak Test
Correct Answer: B
Question #10
Who is ultimately responsible for identifying specific risks and threats for the pressure testing process?
- A . Regulatory authorities
- B . Pipeline vendors
- C . Inspection service personnel
- D . The pipeline operator
Correct Answer: D