Practice Free PK0-005 Exam Online Questions
Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?
- A . Project status report
- B . Project evaluation review
- C . Project management software
- D . Requirements traceability matrix
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration.
Which of the following should be established to best meet this goal?
- A . Task log
- B . Cadence
- C . Milestones
- D . Work breakdown structure
The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget.
Which of the following best describes what the project manager should do to assist the client?
- A . Grant the client access to the project repository.
- B . Create a chat to communicate in real time.
- C . Schedule a weekly status meeting.
- D . Send a weekly status report by email.
Which of the following is a capital expense?
- A . Building lease
- B . Building purchase
- C . Building maintenance
- D . Building insurance
A company purchases new software. The project manager needs to present the new software’s features to the stakeholders.
Which of the following meeting types should the project manager and stakeholders have?
- A . Status
- B . Focus
- C . Brainstorming
- D . Informative
A team member identifies a critical issue in production.
Which of the following should the project manager apply?
- A . Compliance check
- B . Release plan
- C . Rollback plan
- D . Validation check
During a quality analysis review, the causes of several issues have been highlighted.
Which of the following should the project manager use to identify the MOST important causes?
- A . Ishikawa diagram
- B . Scatter diagram
- C . Pareto chart
- D . Decision tree
During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item.
Which of the following documents should the project manager update next?
- A . Schedule
- B . Status report
- C . Issue log
- D . Task board
A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks.
Which of the following should the project manager provide?
- A . Project network diagram
- B . Fishbone diagram
- C . Burndown chart
- D . Milestone chart
A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date.
Which of the following should the project manager do first?
- A . Hold the project until the devices are delivered.
- B . Evaluate the impact to baselines.
- C . Request another supplier to ship devices.
- D . Update the project timeline with a new project end date.